خلاصہ

I am Graduate Engineer (Metallurgy and Materials) with more than 11 years’ experience in field of Inspection/Integrity for Oil and Gas Sector. I have multiple International Certifications like API-580,510,570, CSWIP-3.1 Level II, and ASNT Level II RT UT MT PT.
I am currently working as Senior Engineer (Asset Integrity) in Inspection Management Department, Qatar Petroleum NGL Plant Mesaieed, Qatar on behalf of National Petroleum Services (Manpower Supplier for Qatar Petroleum). I am responsible for the integrity and inspection planning of 3000+ equipment’s that include pressure vessels, storage tanks, columns, heaters, heat exchangers, plant process piping and pipe line. IMS team is responsible for risk management of pressure equipments through inspection and Risk Mitigation measures using RBI (Risk Based Inspection) methodology API-580.
Also I am actively involved in the Plant Unit NGL-4 Shut Down-2017 (Major) and performed inspection of pressure vessels Heat exchangers coolers etc.
I worked Inspection Manager, Velosi Integrity & Safety Pakistan. I was leading team of Engineers and Inspectors involved in field inspection and RBI projects. I was responsible for reporting the KPI and monthly progress to higher management for budget allocation. Our major clients were Nishat Power, Lalpir Thermal Power Plant, PSO Pakistan etc.
I worked as Senior Inspection Engineer, Bureau Veritas Pakistan. I was involved in fabrication as well as in-service inspection of pressure equipment’s and steel structures.
I worked as Senior QA/QC Engineer, DDFC Pvt Limited (ASME Stamp Certified Shop) I was involved in the Inspection ,NDT and QA/QC documentation of pressure vessels (ASME U stamp & Non U stamp) Heat Exchangers, Boilers Steel Structures etc.
I worked as QA/QC Engineer with Descon Engineering Pvt Limited (ASME Stamp Workshop) I was involved in inspection activities of Boilers Steel structure Heat Exchanger Cooler etc.

پراجیکٹس

TPI OF STEAM & MUD DRUM FOR WATER TUBE BOILER: ICI SODA ASH PLANT
NGL-4 Shut Down 2017

تجربہ

کمپنی کا لوگو
Senior Inspection/Asset Integrity Engineer
National Petroleum Services Qatar (Manpower supplier for Qatar Petroleum)
ستمبر ۲۰۱۵ - موجودہ | Umm Said, Qatar

I am working as Senior Engineer (Asset Integrity), IMS Department Qatar Petroleum on behalf of NPS. IMS department is responsible for maintaining the RISK of pressure equipment’s at acceptable level through inspection and risk mitigation measures. Lloyd’s registered software Capstone RBMI (Reliability Based Mechanical Integrity) is used for Risk Based Inspection methodology. I am responsible for inspection management, defining priority for inspections, critical analysis, defining damage mechanisms for particular equipment, assisting inspection teams, developing inspection plan, defining inspection task, preparing shutdown scope challenge as well as planning the inspection activities for 3000+ pressure equipment’s at NGL plant Mesaieed Qatar. I am also involved in field inspections to monitor and identify the possible degradation mechanisms
Below are the details of responsibilities:
To maintain RISK of pressure equipments at acceptable level using RBMI methodology involving inspection and Risk Mitigation measures
1. To update inspection reports and inspection confidence in RBMI based on the results of inspection
2. Enter potential damage mechanisms and corrosion rates into Capstone software as per API guidelines defined in a corrosion study in order to update risk ranking.
3. To run criticality of pressure equipment’s and update the inspection plans
4. Support the Senior Discipline Engineers in the assessment of problems both technical and operational by sourcing information, progressing actions, notification of actions etc.
5. Planning for shutdowns and identifying inspection criticality
6. Identifies critical process equipment and piping.
7. Establishes and executes appropriate Inspection / NDT plan.
8. Prepares scope of work for major, modular turnarounds.
9 Involved In inspection of Pressure vessels heat exchangers coolers during NGL-4 shutdown 2017

کمپنی کا لوگو
Inspection Manager (VISP)
Applus+ Velosi Pakistan
دسمبر ۲۰۱۴ - اگست ۲۰۱۵ | Lahore, Pakistan

Worked as Manager Velosi Safety and Integrity Pakistan and involved in following assignments:
1. Supervise Inspection team, comprising of both Inspectors and Senior Inspectors
2. Monitor and report on throughput through department, in line with set targets
3. First point of contact for Inspection related queries/requests
4. Review resource requirements within department and communicate
5. Make informed decisions on acceptance on a day to day basis, within the department.
6. Disseminate information within Inspection Team on a regular basis
7. Review and identify needs of Inspection department with regards to metrology and gauging
8. Undertake other related duties as required

کمپنی کا لوگو
Senior Inspection Engineer
Bureau Veritas Pakistan
مارچ ۲۰۱۲ - نومبر ۲۰۱۴ | Lahore, Pakistan

WITNESS OF WQT (Approx. 1000 Welders) FOR WEATHERFORD

Approved by Weatherford Iraq, I witness WQT of welders at M/s Ravi Green Engineering Lahore for construction of steel tanks in Iraq

IN-SERVICE INSPECTION OF LPG STORAGE TANKS
In-service inspection of LPG storage tanks (14 Numbers) as per API-510 & OGRA, Pakistan requlations

TPI DURING FABRICATION OF FIN-FAN COOLERS FOR JORD UAE
Approved by Jord UAE for the fabrication of fin fan coolers at Descon Engineering Limited LMW
i) Material Verification and Review and approval of MTR’s
ii) Review and approval of QIP, WPS, WQT QA/QC procedures etc.
iii) Fabrication inspection of coolers as per approved QIP
Iv) Witness of final HPT
v) Final Assembly inspection of coolers


TPI OF STEAM & MUD DRUM FOR WATER TUBE BOILER: ICI SODA ASH PLANT
Due to condition of boiler, ICI decided to replace steam drum, mud drum and tubes of water tube boiler.
Boiler was constructed as per BSEN 12952.
i) WPS and WQT preparation, witnessing qualification and Lab testing as per BSEN.
ii) Fabrication inspection as per as built drawing
iii) witness of hydrostatic pressure test at site

INSPECTION AND MONITORING DURING REPAIR OF BOILER:
During Inspection of boiler severe metal loss was observed in one boiler and repair was recommended to restore the minimum thickness as recommended by design code Activities include:
I) Preparation of repair procedure
ii) QIP approval
iii) Inspection after weld build up
iv) NDT (DPT) of weld build up area
v) Localized PWHT of Boiler as per approved procedure
vi) Final HPT Of boiler

IN-SERVICE INSPECTION OF PRERSSURE VESSELS, COLUMNS AND BOILER: PAKISTAN PETROLEUM LIMITED SUI GAS FIELD
On-stream inspection of pressure equipment’s (15 pressure vessels, 8 columns 01 Boiler) at PPL SUI
Include following activities
Review of inspection history
On-stream inspection visual

کمپنی کا لوگو
Senior QA/QC Engineer
DDFC Pvt Limited Pakistan
جولائی ۲۰۰۸ - فروری ۲۰۱۲ | Lahore, Pakistan

• To study Job Specifications and prepare Quality Inspection Plans and Manufacturing Travelers and to ensure implementation of Quality Systems at shop level.
• To depute Quality Control Inspector for shop inspections & also carryout inspections whenever needed as per QCP
• To lead a team of Quality Control Inspectors and to manage department resources.
• To coordinate with material inspectors for compilation of material verification record.
• To verify received MTR from ASME Authorized Inspector.
• To co-ordinate testing of material, if required from third parties
• To prepare inspection report after complete inspection of material.
• To carryout welding inspection after complete fabrication of Job.
• To ensure that non-conformance raised are logged adequately and make follow up action till closure of the same.
• To analyze monthly data of non-conformance for improvement.
• To follow up items placed on HOLD during incoming, in process and final stages of inspections.
RESPONSIBILITIES AS NDE ENGINEER:
RESPONCIBILITIES AS INSPECTION/NDE ENGINEER (DELSER PVT LTD)
As Inspection/NDE Engineer in DELSER Pvt. Ltd I performed following major assignments:

• ULTRASONIC TESTING AT BESTWAY CEMENT:
Performed Ultrasonic Testing of Cement Kiln Roller Shafts, Support Roller, Tires, Crane Hook Pin etc as per ASME Sec V Art 5 & 23

• ULTRASONIC TESTING AT LAFARGE PAKISTAN CEMENT:
Performed Ultrasonic Testing of Cement Kiln Roller Shafts, Support Roller, Tires, Crane Hook Pin etc as per ASME Sec V Art 5 & 23

• ULTRASONIC TESTING OF AMMONIA VESSEL:
Performed Ultrasonic Testing of complete vessel welds as per ASME Sec.VIII Div I

• INSPECTION & ULTRASONIC TESTING OF LIGAMENT JOINT OF 70 TPH WATER TUBE BOILER:
Performed inspection and ultrasonic testing of ligament joint of Water Tube Boiler at PPL SUI.

کمپنی کا لوگو
Quality Assurance/Quality Control Engineer
Descon Engineering Limited (LMW)
اپریل ۲۰۰٦ - جولائی ۲۰۰۸ | Lahore, Pakistan

Worked on different Standards (ASME, BS, Dutch Rules for Pressure Vessels etc):
• To study project Specification and to prepare Quality Inspection Plan of every project
• To carryout shop inspection and to prepare required documents.
• To verify material to ASME Authorize Inspector.
• To review Material Test reports received from suppliers as per ASME SEC II PART I.
• To verify material to ASME Authorize Inspector.
• To verify received MTR from ASME Authorized Inspector.
• To prepare PWHT Specifications as per standards and review of PWHT graph.
• To prepare IDM (Inspection Data Manual) &review different reports
• For Non destructive testing (RT, DPT, UT, MPI) coordination.

MAJOR PROJECTS
• Heat Exchanger for FFC.
• HP Steam Drum , LP Steam Drums, Blow Down Tank and Flash Tank for NeM Project
• Twins Steam Drum for NeM Project.
• Steel Structure for KTI
• C.S, S.S & Duplex & SS piping for BHP Billiton
• OGDCL Vessels.
• Heat Exchangers, Vessels, Coolers and Skids for BHP Billiton.
• Heat Exchangers and Vessels for Fauji Fertilizer Bin Qasim.
• Coolers and Heat Exchanger for OMV
• Heat Exchangers, Drums and Tower for Bosicor PVT. Limited.
• Heat Exchangers and Vessels for FFC.
• 30 TPH Water tube Boiler for “Gul Ahmed”.
• Waste Heat Smoke Tube Boiler for Saudi Paper Mil

تعلیم

University of Engineering & Technology
بیچلرز, , Metallurgical and Materials Engineering‎
2005

پیشہ ورانہ مہارتیں

ماہر Asset Integrity
ماہر Planning / Design
ماہر QA/QC

زبانیں

ماہر اردو
ماہر انگریزی

آپ کن کمپنیز کی پیروی کر رہے ہیں