To acquire a demanding position in an environment where I can best utilize my skills and education for the growth of the organization
▪ Responsible for the implementation, monitor,ing and coordination of all
operation via SG Wind SCADA and BOP SCADA and all electrical
related work at the site.
▪ Understanding and working on Goldwind and Siemens Gamesa Central
Monitor System SCADA.
▪ Inspection of all electrical equipment such as Transformers, Switch
Boxes, Junction Boxes, AIS, GSU, RMU and surge arrestors, etc.
▪ Manage, control, and monitor SG Wind SCADA, BOP SCADA, equipment,
alarms and faults.
▪ Remote monitoring of Wind Turbines via Siemens Gamesa SCADA system
and escalation of all important system alerts.
▪ Reporting and documentation
▪ Inspection and monitoring of unit pre-startup, startup, and shutdown
operations in compliance with SOP through DCS and Local.
▪ Updating rectification faults & Maintenance work on a wind turbines in
reports.
▪ Generating Permit to work (PTWs) and LOTO in compliance with EHS
policies Supervising
▪ Participate in day-to-day site activities
▪ Comply with all EHS policies and procedures to ensure a safe and productive work site
▪ Performed different actions in coordination with NPCC/RCC.
▪ Performed Shift duties and day closing activities individually in the control
room.
▪ Performed preventative maintenance activities for the smooth running of
the complex.
▪ Installation, testing and commissioning of substation equipment Power Transformer(60MVA), CT and PT, isolator and Circuit Breaker(SF6).
▪ Installation and testing of static VAR compensators area equipment.
▪ Installation and Inspection of all electrical equipment such as switch boxes, junction boxes, switchgear, GSU and surge arrestors etc
▪ Installation of MV, LV, Telecom and Central Control Room equipment.
▪ Testing and Commissioning of Overhead lines.
▪ Review the layout of lighting, cable laying, communication network, fire alarm and earthing.
▪ Earthing of Wind Turbine Generator (WTG), GSU, AIS control building and Auxiliary building.
▪ MV and LV cable laying and termination.
▪ Cables trench and cable laying work.
▪ HVAC piping troubleshooting and firefighting drawings
▪ Monitoring tests as per engineering drawings, standards, and specifications for the quality control of the project development
▪ Managing time schedules instructions and advice.
▪ Site visits and coordination with the engineers.
▪ Attended weekly progress subcontractor meetings to discuss the vital issues related to the project
▪ Rendered technical drawings and electrical system specifications exceed ing company standards.
▪ Review the layout of lighting, cable laying, communication network, fire alarm, and earthing.
▪ Managing stringing, erection, and optical Fibre ground wire of the tower.
▪ Checking the proper insulation and tower materials.
▪ Coordinate with the coworkers and organization to maintain a smooth workflow.
▪ Check work quality and compliance with the design specifications
Operation and Maintenance
Capacitor Banks Testing by using Clamp Meter(KVA, KVAR, Current) for Power Factor Control
Testing on Grid and documentation.