An organized and self-motivated graduate of Electrical Engineering. Looking for a responsible career opportunity to fully utilize my knowledge and managing skills while contributing to the organizational growth.
Job Scope & Task Completed.
I worked as a performer at the following activities.
Compression Facility work Execution Plane.
E&I Work Execution, Including Installation and Pre-Commissioning of MCC Panels, Switch Gears, Motors.
Process & F&G Instruments Installation & Testing, EWS & OWS Installation & Commissioning and Control Works.
Unit Control Panel and Compressor Skid Pre-Commissioning.
Preparation of Track Sheets, Measurement Sheets & Invoices.
Lead the E&I Technical Team to resolve the discrepancies in Vendor Drawings & Schedules.
Insulation resistance Test, Loop Test, HART Test, Secondary Injection Test, Primary Injection Test and ESDV Testing.
Rectified the comments & findings of Factory Acceptance Test.
System Check, Pressure Testing, Functional Testing and Cause and Effects Testing of Relays, Trips, Actuators & Alarms.
Dry Commissioning and SAT (Site Acceptance Test).
Commissioning of Nashpa Gas Compression Facility.