I am an Electrical Engineer having +5 year of experience in analyzing technical drawings, interpreting specifications, prepare and review equipment along with material parameters, C-Part, MEP and Power plant, writing up reports, MOM, MOU, maintain the shipments and billing of contractors during project of PCL Line-3 as a project engineer. Testing, evaluating, modifying and calibrating of gas analyzer, AQM analyzer, dust analyzer, wave feeders, X-ray and online analyzer. perform effective analysis of preventive, corrective, predictive and reactive (run-to-failure) maintenance of instrumentation problems in the pre-heater, raw mill and coal mill area.
To generate and maintain the list of NCRs, pending jobs and punch list issued by PCL team during inspection and commissioning.
Assist the CDI team in the commissioning of Kiln inlet, Precalciner, Pre-heater outlet and coal mill gas analyzers.
Installation of AQM analyzer with the help of PakEnviro and commissioning of AQMS (Air Quality monitoring System) on the demand of EPA (Environmental Protection Authority).
Monitoring operation, Preventive, Corrective, Predictive and Reactive (run-to-failure)
maintenance of Kiln inlet, Precalciner, pre-heater outlet and coal mill gas analyzers.
Perform effective analysis of maintenance of instrumentation problems in the Pre-heater and coal Mill area.
Preventive, Corrective, Predictive maintenance and monitoring operation of online analyzer, xray analyzer and dust hunter of SICK of whole plant.
Preventive, Predictive and corrective maintenance of pressure sensors, temperature sensors, level sensors, flow sensors and actuators of Raw Mill, Coal Mill, Preheater and Kiln area.
Calibration and changing in the feed rate and set point of Schenck wave feeder of Raw mill proportional silo on the demand of Production department.
Assist in Purchase indents, Move order and Approval summary sheets through ERP System.
Day-to-day assistance to General Manager Project in the delivery of projects.
Work closely and effectively with clients and internal project teams.
Generate invoices for clients based on services rendered and in coordination with the Project Manager.
Prepare written estimates for clients based on labor, materials, equipment and other expenses.
Prepare and manage project execution plans, organization charts and status reports.
Assist the GMP to maintain the documents and coordinate with DES for EPA approval.
Assist the GMP to arrange the list of shipments and assist in making the plant summary for payment of shipment.
Deal with CDI and government departments for the issuance of NOC and invitation letters of Chinese.
Assist in making comparison statement for supplier (Foreign and Local).
Assist the GMP in verification of payment of CDI.
Maintain and rearrange the AutoCAD drawing according to PCL requirement.
Prepare written estimates for clients based on labor, materials, equipment and other expenses.
Prepare the organogram for PCL Line-3.
Assist the HOD Electrical and instrumentation to arrange and listed the required documents of 132-KV Grid for getting the NOC from Electrical Inspector of FESCO.
Assist the HOD E&I Line-3 for arranging the required documents for getting the approval of energization of 132-KV Grid from FESCO.
Assist the HOD E&I in arranging and listing the documents of getting approval for the extension of water for the process of Line-3 with help of DES.
Maintain the drawings and manuals provided by OEM for the whole plant Line-3.
To generate and maintain the list of NCRs issued by PCL team during inspection and commissioning.
Collect the data of pending jobs from area incharges and maintain the list of pending jobs and punch list with estimated cost.
Team member of AHL who Install the Final Inspection Bench with help of Japanese Team.
Supervise & manage the employees in paint shop, Assembly shop and final test bench for smooth operation of plant.
Monitoring operation, Preventive, Corrective and Predictive maintenance of motors, actuators, temperature sensors, level sensors and flow sensors of boilers of Paint Shop, Engine Assembly Shop and casting.
Preventive and Corrective maintenance of final test bench, conveyor belt and engine assembly area during operation.
Supervise the team in the installation and commissioning of cargo lift with the help of a team of Sigma International.
Handled Safety Audit done by the Team of Atlas Honda Japan.