• Have more than12 years experience on different types of project throughout the country.
• Currently working as Project Director on the 100 bedded hospital construction project at SKardu.
• Worked on the construction Supervision of 14MW Hydropower Project at Naltar-V Gilgit.
• Worked on the Hydrpower enhancement project with Water and Power Department Gilgit Baltistan.
• Having vast experience on the design of Hydropower project with a Consultant and have assisted in design the 26MW Shagarthang Hydropower Skardu and Pahsdan Dam Afghanistan.
• Enthusiastic and dedication on each project with the acquired knowledge and experiences.
• Responsible for proper cooperation and coordination with Client, Consultant and Contractors team to ensure proper, correct and speedy completion of project.
Major Responsibilities:
• General management and administration related to project.
• Responsible for overall planning and implementation of Project
• Responsible to Coordinate and communicate with Consultant and Contractor regarding project progress and issues.
• Detailed supervision of the internal and external electrification, HVAC, Plumbing works and civil works of the project as per international standard.
• Managing the project budget and estimation for future project development.
• Responsible for technical monitoring of all Electrical works, HVAC and plumbing works as per specification made by SEM.
• Responsible to provide engineering and technical supports to all the electrical and HVAC teams at site.
• Responsible for preparation of maintaining project record of MOM(Minutes of Meeting), Submittal status, Material status, Shop Drawings status, As build Drawings Status(ABDs), Progress reports and Non Compliance Reports.
• Responsible to conduct testing and commissioning of all electrical, plumbing and HVAC works as per specification.
• Ensuring, in principle that all site works are done according to all applicable quality standards.
Major Responsibilities:
• Detailed supervision of the internal and external electrification, HVAC and Plumbing works of the project as per international standard.
• Responsible to provide engineering and technical supports to all the electrical and plumbing work teams at site.
• Responsible for proper cooperation and coordination with Client, FND and Contractors team to ensure proper, correct and speedy completion of project.
• Preparation of daily, weekly and monthly progress reports
• Verification of Contractors Running bill as per measurement at site.
• Interpretation of design drawings and specifications and ensure their proper translation into shop drawings by the contractor
• Responsible for preparation of maintaining project record of MOM(Minutes of Meeting), Submittal status, Material status, Shop Drawings status, As build Drawings Status(ABDs), Progress reports and Non Compliance Reports.
• Ensuring, in principle that all site works are done according to all applicable quality standards.
Major Responsibilities:
• Supervision of installation and commissioning of Turbine, Generator and Auxiliary System
• Conduct Pre-Commissioning and Commissioning Test of Rotor and stator of each Generator
• Supervision of installation, testing and commissioning of Switch yard and Control Room Equipment.
• Supervision of fabrication and Installation works of 4.12 km penstock line.
• Inspection of Welded Joints of pipes through UT as per ASME standards
• Inspection of Paints on Penstock pipes through DFT test.
• Supervision of installation and commissioning of electrical equipment at two Grid Stations (Nomal and Gilgit) and their inter connections.
• Supervision of installation Earthing System in Grid stations, Switch yard and Power House
• Supervision of Survey, planning and spotting of 28 km long 132 kV transmission line.
• Supervision of Erection and stringing of 132 kV ZM Towers
• Checking and vetting of material reached at site.
• Quality control of all installation works at site.
• Physical verification of Contractor’s interim payment certificate (IPC)
• Preparation of monthly progress report.
Major Responsibilities:
• Design, repair/replacement of Protection and Instrumentation System of hydel stations in GB
• Supervision of Repairing and rewinding of ac Synchronous Generator up to 1 MW.
• Rewinding, repair and testing of Generators and Transformer.
• Preparation of Diagnostic Report of Hydel Station.
• Installation of VCBs and protective equipment in various power houses in GB.
• Extensive knowledge in preparing Equipment Layouts, Equipment and fabrication drawings
• Technical Support during procurement, manufacturing, installation and commissioning
• Reporting to Executive Engineer for site status/ site related issues if any.
• Worked on the preparation of PC-1 of Establishment of E/M Laboratory at GBHEW.
• Preparation of PC-I and PC-IV proforma of different project.
Projects:
Shagharthang Hydro Power Project (26 MW)
Thak Hydro Power Project (06 MW)
External and Internal Electrification of the Colonies of the Pashdan and Machalgo Dam Afghanistan
External and Internal Electrification of Staff Colonies of Diamer Basha Dam
Major Responsibilities:
26MW Shagarthang Hydropower Project
• Preparation of Engineering Design for 26MW Power Station with 3 units of 10.22MVA each, 66 kV switchyard with Double Bus Single Breaker Scheme and 66 kV T/L Interconnection with Grid Station.
06MW Thak Chilas Hydropower Project
• Engineering Design of 06MW Power Plant with 3 units of 2MW each, 33 kV switchyard with Single Bus Single Breaker Scheme due to small plant capacity and Double Circuit 33 kV T/L Interconnection with Grid Station.
External and Internal Electrification of the Colonies of the Pashdan and Machalgo Dam Afghanistan
• Preliminary Design of Distribution system (HT & LT).
• Preparation of Bill of Quantities.
• Planning and routing of H.T & L.T underground Cable
• Preparation of electrical drawings
• Design of Street Lighting System in the area.
• Internal electrification of all buildings including offices.
• Monitoring the Distribution Companies Performance with reference to recovery, line losses, extra billing and accidents.
• Implementation of rural electrification program
• Deals with Technical and Non-technical complaints related to WAPDA and other distribution Companies
• Implementation of energy management & conservation programs.
• Safety Plans for Workers/Systems and insurance of their implementation in the field.
• Renovation & Rehabilitation of Distribution System.
• Installation of Gen sets on site.
• Coordination of clients, customer to check the status of site.
• Assist the team leader in supervision of work.
• Provide the entire electrical solutions as per requirement
• Collection of data from field for load for future load generation.
• Preparation of Project Schedules, in coordination with all project team participants from different regions