JIzan Refinery & Terminal Project

تجربہ

کمپنی کا لوگو
Project Engineer
China Harbour Engineering Limited
فروری ۲۰۱٦ - موجودہ | Jizan Economic City, Saudi Arabia

Participated in Project review meetings, assisted Project Manager in monthly status
Report preparation
• Liaise with the Project Management team Saudi Aramco to discuss sequence of work.
• Planning & Coordination of MEP and Civil works which includes Preparing &
Monitoring of Construction Schedule in Primavera
• Developed the detailed schedules for all MEP activities
• Worked on Project Planning/scheduling and monitoring on Primavera
• Performed the critical path analysis and identified the critical activities
• Created the Project based line
• Prepared the Project Plan/ Schedule as per the Project team directions
• Created the work break down structure of each task
• Assigned duration to all the activities in each task using three point formula or Project
Manager advice
• Generated reports on Weekly/Monthly/Daily basis which involves ‘S’-curves for client
& reviewing of management
• Closely monitored daily progress using Primavera & making delay analysis reports.
• Performed Project Planning and Monitoring on Primavera
• Performed the Project Procurement
• Performed the Site Supervision and taking daily Progress report.
• Maintained the Project Issue Log Sheet
• Worked on the Project Change management

کمپنی کا لوگو
Mechanical Engineer
Khyber Pakhtunkhwa Oil & Gas Company Limited
جنوری ۲۰۱۴ - جنوری ۲۰۱٦ | Peshawar, Pakistan

Played an important role in establishment of 800 MW Gas Turbine Combine Cycle Power Plant in Kohat region of KPK Province in Coordination with PEDO, Energy & Power Department Government of KP
Consultant: Energy Marketing Group USA. Contractor: Daewoo & Hyundai Engineering Pakistan.
Project Management Responsibilities
• Participated in Project review meetings, assisted Project Manager in monthly status reports preparation.
• Worked on Project data acquisition, analysis and storage.
• Worked on Project Planning/scheduling and monitoring on Primavera P6.
• Selected the most Feasible site for 800MW Project in Kohat region of KPK Province...
• Monitored and Assisted Consultant on in conduction of EIA, SIA and DIA for different projects.
• Produced Feasibility studies and Prepared RFP, s for Gas seepages in KPK District
Procurement Responsibilities:
• Responsible for day to day Purchase operations.
• Perform project cost forecasts, cost tracking, monitoring and controls.
• Support CFO in ensuring that inter-departmental cost allocations are in line with company policy.
• Establish and maintain systems for cost-sensitivity analysis and early-warning of cost-overruns.
• Invite, assess, and award/recommend supplier tenders, bids. Quotations and proposals.
• Establish and negotiate contract terms and conditions, and maintain supplier relationships.
• Prepare and maintain purchasing records, reports and price lists.
• Administer contract performance, including delivery, receipt, warranty, damages and insurance.
• Prepared the RFP’s of Owner Engineers team, EPC & Non EPC services for Project
Quality, Health & Safety Responsibilities:
• Assessed the contractor’s quality system, assisted in preparation of QA documents, making the ITP, s and inspection of equipment’s with the third party.
• Maintained the record of all mechanical installation RFI, s.
• Helped the inspectors for raising the RFI.
• Implemented Client Safety Plan on site.
• Checked qualifica

کمپنی کا لوگو
Shift Engineer
CIEL Wood Works(pvt) Limited
اگست ۲۰۱۳ - دسمبر ۲۰۱۳ | Peshawar, Pakistan

• Prepared the Production Plan
• Monitored the Quality Test
• Prepared Daily Production report
• Monitored all the maintenance activities of the Plant
• PPE Compliance of all the workers
• Accident and incident investigation
• Maintained the proper housekeeping and waste management.
• Developed & introduced Permit to work documentation
• Developed and implemented the HSE culture across the company
• Monitored and surveillance for equipment guarding, surveillance of housekeeping
• Conducted emergency drills as required

تعلیم

PMI Islambad
سرٹیفیکیشن, PMP‎
Project Management Professional
مکمل
2015
NWFP University of Engineering & Technology
بیچلرز, , Mechanical Engineering‎
EHS, industrial management, maintenance engineering
CGPA 2.1/4
2013

پیشہ ورانہ مہارتیں

ماہر Handling Assignments
متوسط LTN
متوسط Primavera P6 Project Planning

زبانیں

ماہر اردو
ابتدائی چینی
ماہر انگریزی

آپ کن کمپنیز کی پیروی کر رہے ہیں