*Track record exceeding goals, earning high stakeholder/client satisfaction rating. *Knowledge of resource utilization and control.
*Good operational planning and time management skills. *Manage the projects simultaneously without compromising on standards and quality.
*Ability to ensure standards and specifications are met.
*Ability to work with colleagues to deliver project and operational performance.
*Sound knowledge of construction practices and standards.
*Deep involvement in addressing Construction methodology, Method Statements,Project Quality Plan, Safety Plan, Schedules and Compliance with Project objectives.
*Organize, direct and efficiently use all resources, including subcontractors and suppliers, delivering the highest standard of workmanship and value for money.
Manage the Construction work for the Pioneer Cement Plant 6700TPD Following Structure.
Preheater,Kiln,Clinker Cooler,Lime Stone Crusher,Cement Silos,CCR Main Building,Ware House, Workshop Building.
Construction of LPG new Train-2 and Amine Unit complete the civil work Compressor Foundation,Vessel Skid,Pipe Rack,Pipe Slipper,Pipe Line,Cable Trench,Duct Bank,Pipe Culvert.
Manage the civil work for Le-Meridien 5-Star Hotel 14th story and Work on Bio Medical Research Center a project of KACST King Abdul Aziz City for the Science and Technology.
Foundation,RCC Slab,Sheir Wall,Circular Column,Stair,Positioning,Retaining Wall.Excavation and Back filling.
construction of Riyadh Power Plant 11 (PP11). The power plant will add another 1,200MW to SEC\\\'s already impressive complex of plants.Supervise the TR Compound and Infrastructure all over the project Fire Wall,RCC Under Ground Tanks,Pipe Culvert,Road X-ING,Cable Trench,Pr-casting of Manhole,Trench Cover all over the Project.
Work as a In charge of Area B-200 Burzan Chemical Refinery Manage the the following structure work.
Pipe Rack Double Decker, Tanks and Dike Wall,U/G Pits,RCC Frame Structure,Under Ground Pipe Line,Cable Trenches.
ENGRO Fertilizers Ltd built a new fertilizer plant here which is the world\'s largest ammonia/urea plant. built a prill tower about 125 meters high.
In charge all the U/G Pipe Line,Cable Trenches,Pipe Support, and Area completion hand over to Mechanical team.
Construction of World Trade Center (Geega Mall) and Platinum Square in DHA Phase-11 Piling work ,Heavy Raft 2.3mtr high each pour 200meter cube,Use high strength concrete 10000psi for column use the Plasform Technology 1st time in Pakistan,use dry curing meathead for raft curing also use pouring strip between the two pour of raft.
Work at Jubail Petrochemical Refinery,KRT Project,Gulf Frabi Chemical Refinery, Sharq 3rd Expansion.
Supervise the Structure work for Substation,Vessel Foundation,Pipe Slipper,Pipe Rack,Cooling Water Supply Pipe Line and Fire water Pipe Line.