1. Submission of Interim Claim of PKR 6,936,397,531 Request for Engineer’s Decision under Clause of 67.1 of Contracts of Condition of Fourth Edition of FIDIC 1987.
2. Variation Order.1 Girders [High Quality of Moulds] and Girder Casting Yard [Extra Works] of PKR 1,160,488,768.78 to Lahore Development Authority under Clause 51, 52 and 53 of Fourth Edition of FIDIC 1987.
3. Variation Order.2 Transom [High Quality of Moulds] and Transom Casting Yard [Extra Works] of PKR 520,150,389.00 Lahore Development Authority under Clause 51, 52 and 53 of Fourth Edition of FIDIC 1987.
4. Variation Order.3 Additional Girders 6 nos. [High Quality Moulds] and Girder Casting Yard [Extra Works] of PKR 221,977,622 to Lahore Development Authority under Clause 51, 52 and 53 of Fourth Edition of FIDIC 1987.
5. Variation Order.4 Bill no.7 of PKR 124,230,952.31 to Lahore Development Authority under Clause 51, 52 and 53 of Fourth Edition of FIDIC 1987.
6. Variation Order.5 NON-BOQ Items [Extra Items] to Lahore Development Authority under Clause 51, 52 and 53 of Fourth Edition of FIDIC 1987.
7. Request for Interim Extension of Time due to Employer’s Risk Events for 214 days to Lahore Development Authority under Clause 6.3, 12.2, 20.4, 44.1, 51.1, 56.1 of Fourth Edition of FIDIC 1987.